Community Recreation Center

Share Community Recreation Center on Facebook Share Community Recreation Center on Twitter Share Community Recreation Center on Linkedin Email Community Recreation Center link

The City of Grand Junction Parks and Recreation invited residents to help shape the identity of the new Community Recreation Center through an online survey and a community meeting. The survey gathered input on naming and visual style. On April 1, 2025, community members attended an interactive meeting at the Lincoln Park Barn, where they received project updates, shared feedback on branding elements, and explored ways to stay involved, including signing up for future construction tours. View a live recording of the presentation below.



A groundbreaking event for the new facility was held on Saturday, June 1, at Matchett Park.

City Council adopted the final plan in November of 2022. This became the basis for an April 2023 ballot initiative approved by voters that included a 0.14% sales tax increase and the debt necessary to make the facility a reality. Community engagement over the course of several decades including meetings, presentations, focus groups, and opportunities for input has resulted in the final design of the new Community Recreation Center.

Barker Rinker Seacat, the lead architect headed up the design team that included many local engineers and architects, was selected after a Request for Proposals (RFP) was distributed in 2023. The group used the concept design from the 2022 CRC plan as the basis for design incorporating the public feedback provided over the years. Following the public engagement session last fall, the design is complete and will be presented to the community on April 30, 2024.

The other important aspect of the project is process of identifying the Construction Manager/General Contractor which was conducted through another RFP resulting in the selection of FCI. FCI will provide cost estimating to keep the project on budget, they will manage the groundbreaking this summer, and they will oversee approximately two years of construction. The approximate grand opening of the Grand Junction Community Recreation Center is scheduled for mid-2026.

Curious to see inside the Community Recreation Center? Take a virtual tour of the facility!


Presentation from the April 30 public meeting.


The City of Grand Junction Parks and Recreation invited residents to help shape the identity of the new Community Recreation Center through an online survey and a community meeting. The survey gathered input on naming and visual style. On April 1, 2025, community members attended an interactive meeting at the Lincoln Park Barn, where they received project updates, shared feedback on branding elements, and explored ways to stay involved, including signing up for future construction tours. View a live recording of the presentation below.



A groundbreaking event for the new facility was held on Saturday, June 1, at Matchett Park.

City Council adopted the final plan in November of 2022. This became the basis for an April 2023 ballot initiative approved by voters that included a 0.14% sales tax increase and the debt necessary to make the facility a reality. Community engagement over the course of several decades including meetings, presentations, focus groups, and opportunities for input has resulted in the final design of the new Community Recreation Center.

Barker Rinker Seacat, the lead architect headed up the design team that included many local engineers and architects, was selected after a Request for Proposals (RFP) was distributed in 2023. The group used the concept design from the 2022 CRC plan as the basis for design incorporating the public feedback provided over the years. Following the public engagement session last fall, the design is complete and will be presented to the community on April 30, 2024.

The other important aspect of the project is process of identifying the Construction Manager/General Contractor which was conducted through another RFP resulting in the selection of FCI. FCI will provide cost estimating to keep the project on budget, they will manage the groundbreaking this summer, and they will oversee approximately two years of construction. The approximate grand opening of the Grand Junction Community Recreation Center is scheduled for mid-2026.

Curious to see inside the Community Recreation Center? Take a virtual tour of the facility!


Presentation from the April 30 public meeting.


  • October 2025 Community Recreation Center Update

    Share October 2025 Community Recreation Center Update on Facebook Share October 2025 Community Recreation Center Update on Twitter Share October 2025 Community Recreation Center Update on Linkedin Email October 2025 Community Recreation Center Update link

    CRC construction continues to progress. Major milestones in September included:

    • Eldorado Climbing was selected as the installer of the CRC’s climbing walls. There are three wall styles – Rock realistic wall designed to simulate Independence Monument, standard panelized wall, and bouldering wall.
    • The stair tower for the waterslide has begun.
    • All interior walls are framed and, in some areas, the drywall is being hung.

    Next month we will begin hiring for some fulltime positions at the CRC: Customer Service Supervisor and Aquatics Coordinator. Over the next several months, we will onboard eleven full time positions. Beginning in the spring of 2026, we will begin hiring part-time and seasonal staff. Positions include:

    • Guest Service Representative
    • Fitness Instructor
    • Lifeguard
    • Manager on Duty
    • Child Watch Attendant
    • Climbing Wall Attendant
    • Custodian
    • Recreation Leader
    • Swim Lesson Instructor

    All positions will be posted and can be applied for on the City Employment Website.

  • September 2025 Community Recreation Center Update

    Share September 2025 Community Recreation Center Update on Facebook Share September 2025 Community Recreation Center Update on Twitter Share September 2025 Community Recreation Center Update on Linkedin Email September 2025 Community Recreation Center Update link

    CRC construction continues to progress. Major milestones in September included:

    • Eldorado Climbing was selected as the installer of the CRC’s climbing walls. There are three wall styles – Rock realistic wall designed to simulate Independence Monument, standard panelized wall, and bouldering wall.
    • The stair tower for the waterslide has begun.
    • All interior walls are framed and, in some areas, the drywall is being hung.

    Next month we will begin hiring for some fulltime positions at the CRC: Customer Service Supervisor and Aquatics Coordinator. Over the next several months, we will onboard eleven full time positions. Beginning in the spring of 2026, we will begin hiring part-time and seasonal staff. Positions include:

    • Guest Service Representative
    • Fitness Instructor
    • Lifeguard
    • Manager on Duty
    • Child Watch Attendant
    • Climbing Wall Attendant
    • Custodian
    • Recreation Leader
    • Swim Lesson Instructor

    All positions will be posted and can be applied for on the City Employment Website.

  • August 2025 Community Recreation Center Update

    Share August 2025 Community Recreation Center Update on Facebook Share August 2025 Community Recreation Center Update on Twitter Share August 2025 Community Recreation Center Update on Linkedin Email August 2025 Community Recreation Center Update link

    On August 8, the final steel beam was hoisted into place at the Community Recreation Center at Matchett Park, marking a major milestone in the construction process. Covered in hundreds of signatures from community members, partners, and council, this beam is a symbol of the teamwork that brought this project to life. In order to complete the steel structure, the construction team has installed:

    • 577 drilled piers
    • Over 1.4 million pounds of steel
    • 9,268 bolts
    • 4,828 yards of concrete
    • 881,000 pounds of rebar